How do data centre power, build and colocation costs in India compare with other countries?

By Vinod Chacko, Founder and CEO · Last updated

Grid power for large users in India costs about ₹6.2 to ₹10.9 per kWh, a mid-range price (FY2026-27 tariffs). Building is cheap: about US$7.4m per MW, against US$15.2m in the USA (Cushman & Wakefield, 2026). Mumbai colocation costs US$73 to US$105 per kW a month (H1 2025), against US$330 to US$475 in Singapore (Q1 2026).

Key facts

  • In Maharashtra (MSEDCL), large industrial users on high-tension supply pay an average ₹10.88 per kWh (US$0.114). If billed as commercial, they pay ₹16.74 (US$0.176), about 54% more.

    As of FY2026-27. MERC (tariff order, 25 Mar 2026)

  • Singapore's regulated tariff for large users works out at S$0.235 to S$0.246 per kWh all-in (US$0.184 to US$0.192).

    As of Q4 2026. SP Group

  • Building a data centre in India costs about US$7.4m per MW (about ₹70 crore; range US$5.9m to US$9.0m), excluding land and IT equipment. Malaysia is US$9.6m and the USA US$15.2m.

    As of 2026. Cushman & Wakefield cost guides

  • Mumbai colocation rent is ₹7,000 to ₹10,000 per kW a month (US$73 to US$105) for 250 kW to 1 MW, and ₹6,000 to ₹7,500 (US$63 to US$79) for 5 MW or more.

    As of H1 2025. Cushman & Wakefield

  • Colocation asking rents elsewhere: Northern Virginia US$190 to US$235, Frankfurt US$235 to US$265 and Singapore US$330 to US$475 per kW a month.

    As of Q1 2026. CBRE

Rupee to dollar conversions use ₹95.25 per US$ (FBIL reference rate, 13 Oct 2026).

Terms used on this page (12)
Colocation
Renting space, power and cooling in someone else's data centre for your own servers.
Energisation, sanctioned load
Energisation is when the utility actually switches power on. Sanctioned load is the maximum power it has approved for the connection.
DISCOM
A state electricity distribution company. It supplies and bills most large users.
HT, EHV, HV-2
High-tension (usually 11 to 33 kV) and extra-high-voltage supply; higher voltage usually means a lower tariff. HV-2 is Uttar Pradesh's category for large and heavy power users.
Open access, wheeling, cross-subsidy surcharge
Open access lets a large user buy power from a generator other than its DISCOM. Wheeling is the fee for using the DISCOM's wires; the cross-subsidy surcharge compensates the DISCOM for the customer it loses.
Captive, group captive
A power plant at least 26% owned by the users who consume at least 51% of its output. It is exempt from some surcharges.
IPP (independent power producer)
A company that builds and owns power plants and sells the power under long-term contracts, rather than a state utility.
RTC, FDRE
Round-the-clock (RTC) and firm and dispatchable renewable energy (FDRE): green power backed by storage or pumped hydro so it is available at set hours, not only when the sun shines or the wind blows.
FY (Indian financial year)
April to March. FY2026-27 runs from 1 Apr 2026 to 31 Mar 2027.
H1, H2
The first half (January to June) and second half (July to December) of a calendar year.
Lakh, crore
1 lakh is 100,000 and 1 crore is 10 million. ₹1 lakh crore is ₹1 trillion, about US$10.5bn at ₹95.25 per US$.
MEP
Mechanical, electrical and plumbing: the building services trades on a data centre build.

Tariffs, build costs and rent, market by market

Grid power in India is mid-priced, not cheap. Building a data centre is cheap. Colocation rent is low by global standards.

Your real bill depends on the state, the supply voltage and the tariff category the state distribution company (DISCOM) gives your site. Energy is about 65% of data centre operating cost (S&P Global, cited by Cushman & Wakefield).

Green power is now bought mostly from independent power producers (IPPs) under captive deals, and several power companies are building data centres of their own. Who they are, and what round-the-clock green power costs, is in the tables below.

What this means for a GPU cloud

Tariff category is the biggest swing. In Maharashtra a data centre billed as commercial pays about 54% more than one billed as industrial, and several state data centre policies help secure industrial treatment; in Karnataka the current order makes HT commercial slightly cheaper than industrial. Confirm the category per connection, in writing, and compare delivered rupees per kWh.

Grid power for large users: price per kWh

MarketUS$ per kWhAs of
Andhra Pradesh (Visakhapatnam)0.065 to 0.075FY2026-27
Uttar Pradesh (Noida)0.069 to 0.081FY2026-27
Karnataka (Bengaluru)0.079 industry; 0.070 commercialFY2026-27
Telangana (Hyderabad)0.082 to 0.092FY2026-27
Tamil Nadu (Chennai)0.095 to 0.105FY2025-26 rates
Maharashtra (Navi Mumbai, Pune)0.108 to 0.114FY2026-27
Maharashtra, if billed as commercial0.176FY2026-27
USA: Virginia (industrial)0.101Jul 2026
Germany (Frankfurt proxy)0.154H1 2026
Singapore0.184 to 0.192Q4 2026

Indian rows are our all-in estimates from each state's tariff order, for a large user drawing a flat load around the clock. Rupee prices, tariff categories, more countries and every source are under How we got these numbers, below. Foreign rows use different bases, so treat them as a guide, not a like-for-like quote.

How we got these numbers: grid power by market and tariff category

Rupee and local prices, tariff categories and sources for 17 markets
MarketIndicative all-in price per kWhUS$ per kWhBasisAs ofSource
Maharashtra (MSEDCL: Navi Mumbai, Thane-Belapur, Pune)₹10.28 (EHV) to ₹10.88 (HT)0.108 to 0.114Industry at high-tension (HT, 11 to 33 kV) or extra-high voltage (EHV): average billing rate for that sub-category, used to set cross-subsidy. HT industry as a whole averages ₹10.71 in FY27FY2026-27MERC order, 25 Mar 2026
Maharashtra, if billed as commercial₹16.74 (HT)0.176Commercial at high-tension (11 to 33 kV): average billing rate for that sub-category. HT commercial as a whole averages ₹16.78 in FY27FY2026-27MERC order
Tamil Nadu (Chennai)About ₹9.0 (our estimate); ₹9.96 approved average billing rate0.095 to 0.105High-tension industry and IT services (category HT-I), which names data centresFY2025-26 rates; FY2026-27 revision of up to 6% not confirmedTNERC order, 30 Jun 2025
Telangana (Hyderabad)₹7.8 to ₹8.8 (our estimate)0.082 to 0.092High-tension industry (category HT-I(A)), 11 kV to 132 kVFY2026-27TGERC tariff schedule
Uttar Pradesh (Noida, state DISCOMs)₹6.6 to ₹7.7 (our estimate)0.069 to 0.081Large and heavy power users (category HV-2), 11 kV to above 132 kVFY2026-27UPPCL notice of UPERC tariff, Jul 2026
Karnataka (Bengaluru)About ₹7.5 industry; about ₹6.7 commercial (our estimates)0.079; 0.070HT industry; HT commercial is now slightly cheaperFY2026-27KERC order, 27 Mar 2025
Andhra Pradesh (Visakhapatnam)₹6.2 to ₹7.1 (our estimate)0.065 to 0.075High-tension industry, 11 kV to 132 kVFY2026-27APERC order, 25 Mar 2026
SingaporeS$0.235 to S$0.2460.184 to 0.192SP Group regulated tariff for large users at extra-high and high tensionQ4 2026SP Group
Ireland (Dublin proxy)€0.1800.201National non-household average, 70-150 GWh a year, excl. VATH1 2026Eurostat
Germany (Frankfurt proxy)€0.1380.154Same basisH1 2026Eurostat
Netherlands (Amsterdam proxy)€0.1250.140Same basisH1 2026Eurostat
USA: Virginia10.07; 11.68 US cents0.101; 0.117State average, industrial; commercialJul 2026US EIA
USA: Texas7.07; 8.47 US cents0.071; 0.085State average, industrial; commercialJul 2026US EIA
Japan¥28.260.179Business average incl. taxes, not a large-user rateMar 2026GlobalPetrolPrices (low confidence)
MalaysiaRM0.4730.116Business average incl. taxes, not a large-user rateMar 2026GlobalPetrolPrices (low confidence)
UAEAED 0.4050.110Business average incl. taxesMar 2026GlobalPetrolPrices (low confidence)
IndonesiaRp1,114.740.062Business average incl. taxesMar 2026GlobalPetrolPrices (low confidence)

Our Indian all-in estimates assume a flat 24x7 load at 85% load factor and include demand charges and time-of-day effects. They exclude electricity duty, fuel adjustment and open access charges. Exchange rates: ₹95.25, S$1.28, ¥158.1, RM4.09, Rp17,881 per US$ (FBIL and ECB, 13 Oct 2026); AED 3.6725 per US$ (fixed peg); €1 = US$1.119. Foreign rows use different bases, so treat them as a guide, not a like-for-like quote. HT means high-tension supply (usually 11 to 33 kV), EHV extra-high voltage.

Green power and open access: cost building blocks

Renewable purchase prices, open access surcharges, wheeling and the captive exemption
ItemValueUS$As ofSource
Solar bought by MSEDCL₹2.67 to ₹3.04 per kWh0.028 to 0.032FY2026-27 projectionMERC
Firm and dispatchable renewables bought by MSEDCL₹4.46 per kWh0.047FY2026-27 projectionMERC
Cross-subsidy surcharge on third-party open accessMaharashtra ₹2.11; Tamil Nadu ₹1.99; Andhra Pradesh (Vizag DISCOM) ₹1.37 to ₹1.71 per kWh0.014 to 0.022FY2025-26 to FY2026-27MERC; TNERC; APERC
Wheeling charges₹0.81 to ₹1.04 per kWh0.009 to 0.011FY2025-27MERC; TNERC
Round-the-clock (RTC) green power, SECI 1 GW tender₹5.25 to ₹5.26 per kWh at the inter-state grid, before transmission, wheeling and surcharges0.055Aug 2026SECI auction result (pv magazine India)
Green power with 4-hour assured peak supply (SECI FDRE-IX)₹5.99 to ₹6.00 per kWh at the inter-state grid0.063Aug 2026SECI auction result (pv magazine)
Earlier firm and dispatchable renewable (FDRE) tenders₹4.48 to ₹4.70 per kWh (NHPC and NTPC)0.047 to 0.049Nov to Dec 2024Trade press
Inter-state transmission waiver for solar and wind100% if commissioned by 30 Jun 2025, then 75%, 50%, 25%; nil after 30 Jun 2028. A project commissioned between 1 Jul 2026 and 30 Jun 2027 gets 50%. Since Apr 2026, projects delayed by late transmission may be allowed to keep the tier they were duen/a2026Cushman & Wakefield / Invest India; Ministry of Power (Mercom)
Green energy open access threshold100 kW; deemed approval after 15 days (as reported; not checked against each state's rules). The Karnataka High Court struck down the central green open access rules in Jan 2025, so each state regulator's own regulations deciden/a2026Cushman & Wakefield / Invest India
Captive or group captive (26%+ ownership and 51%+ consumption)Exempt from cross-subsidy and additional surchargesn/aElectricity ActCushman & Wakefield / Invest India

Generation and tender rates are benchmarks at the point of supply, not prices a data centre can contract at. RTC tender prices rose by about ₹0.5 to ₹0.8 per kWh between late 2024 and Aug 2026. The landed cost of round-the-clock green power varies by state and structure; we found no sourced all-in figure.

Who supplies green power to Indian data centres

Power companyWhat it suppliesPublic data centre dealsOwn data centre plansAs of
CleanMaxCaptive and group captive solar, wind and hybrid; adding storage and pumped hydroSTT GDC India (more than 130 MW in Tamil Nadu and Maharashtra), Equinix Mumbai (33 MW), Iron Mountain (group captive solar and wind for Mumbai, Pune and Bengaluru, May 2026), Meta (more than 900 MW), Google (125.4 MW)2 GW green compute campus in Kurnool district, Andhra Pradesh: about ₹50,000 crore for 3 GW of wind and solar plus 1 GW of pumped hydro, with a Blackstone-backed Indian GPU cloud anchoring 1 GW of IT load (MoUs, Nov 2026)2024 to Nov 2026
ReNewSolar, wind and hybrid; open access and captiveMicrosoft (437.6 MW, green attributes), Google (150 MW Rajasthan solar)1 GW green hyperscale data centre at Anakapalli, Andhra Pradesh (Nov 2026); 750 MW green data centre park in the Mumbai region, ₹70,000 crore MoU with Maharashtra, phased from 2028 (Oct 2026)Nov 2026
Tata PowerDistribution in Mumbai, transmission, captive renewables, storagePrinceton Digital Group Mumbai (25-year captive deal, 2023); a 2.8 GW data centre pipeline with 18 operators, names not givenNone announcedOct 2026
NTPC Green EnergyRound-the-clock renewables for captive useMoUs with CtrlS (about 2 GW, Nov 2025) and Nxtra by Airtel (Mar 2026); no MW or price terms publishedNone announcedMar 2026
AMPIN Energy TransitionOpen access and inter-state solar-wind hybridNxtra by Airtel: 48 MWdc solar and 24.3 MW wind (2024), then 125.65 MW hybrid in Rajasthan and Karnataka (Jul 2025)None announcedJul 2025
Hexa ClimateCaptive solarDigital Edge Navi Mumbai: up to 83 MW for Phase 1, deliveries from Dec 2026None announcedFeb 2026
Inox Clean (ex-Vibrant Energy)Captive solar and windSify Mumbai (231 MW) and Amazon (300 MW), contracted by Vibrant in 2022None announced2025
Adani Green EnergySolar, wind and battery storage (20.76 GW operating, Sep 2026)Dedicated renewable supply for the Google and AdaniConneX campus at Visakhapatnam (per Adani)Through AdaniConneX, its data centre joint ventureOct 2026
AM Green (AM Group)Firm carbon-free power from renewables and pumped storageNone external1 GW AI campus on YEIDA land in Uttar Pradesh: 350 MW by 2028, 1 GW by 2030Feb 2026
WaareeSolar modules and projects; won 700 MW of peak-assured green power in SECI's FDRE-IX tender (Aug 2026)None publicSet up two data centre companies, Sunstar Data Centers and Aurovault Data Centers (Sep 2026), being moved under listed Waaree Energies (board approval 27 Oct 2026); no site, MW or investment disclosedOct 2026

Public deals only, from company releases, stock exchange filings and trade press. Hyperscalers also buy directly: Amazon reports more than 2 GW contracted in India and Microsoft more than 1,000 MW. Reliance plans to power its Jamnagar AI campus from its own renewables. Most deals are captive or group captive, with the data centre taking a 26% stake, which removes the cross-subsidy and additional surcharges. Plain solar or wind deals usually cover about 40 to 70% of a site's power, so grid supply is still needed.

Construction cost (excluding land and IT equipment)

MarketUS$m per MWRangeSource and date
India (national average)7.4 (about ₹70 crore)5.9 to 9.0Cushman & Wakefield, 2026
Mumbai6.64n/aTurner & Townsend, cited Feb 2026
Indonesia8.36.6 to 11.2Cushman & Wakefield, 2026
Malaysia9.66.9 to 12.0Cushman & Wakefield, 2026
Australia10.07.9 to 12.1Cushman & Wakefield, 2026
Frankfurt11.6n/aTurner & Townsend, Nov 2025
London12.0n/aTurner & Townsend, Nov 2025
Singapore14.5n/aTurner & Townsend, Nov 2025
USA (34 markets)15.211.7 to 18.7Cushman & Wakefield, 2026
Tokyo15.2n/aTurner & Townsend, Nov 2025
Japan (national)16.013.0 to 19.2Cushman & Wakefield, 2026

The two sources use different specifications, so compare within one source. A 100 MW build in India costs about US$220m less than in Malaysia (Cushman & Wakefield). AI-ready builds cost about 7 to 10% more (Turner & Townsend, US data).

Colocation rent (per kW per month)

MarketPriceUS$Deal size and basisAs ofSource
Mumbai₹7,000 to ₹10,000 (250 kW to 1 MW); ₹6,000 to ₹7,500 (5 MW+)73 to 105; 63 to 795-7 kVA racksH1 2025Cushman & Wakefield
Chennai₹7,500 to ₹8,500 (250 kW to 1 MW); ₹6,000 to ₹7,000 (5 MW+)79 to 89; 63 to 73SameH1 2025Cushman & Wakefield
Hyderabad and Delhi NCR₹7,000 to ₹8,500 (250 kW to 1 MW); ₹6,000 to ₹7,000 (5 MW+)73 to 89; 63 to 73SameH1 2025Cushman & Wakefield
Northern VirginiaUS$190 to 235190 to 235250-500 kW; vacancy 0.3%Q1 2026CBRE
FrankfurtUS$235 to 265235 to 265250-500 kW; vacancy 5%Q1 2026CBRE
TokyoAverage US$280280Asking rent; vacancy 6%Q1 2026CBRE
SydneyAverage US$188188Asking rent; vacancy 4.5%Q1 2026CBRE
SingaporeUS$330 to 475 (average US$403)330 to 475Asking rent; vacancy 2%Q1 2026CBRE

Indian figures are the latest city rents Cushman & Wakefield published (H1 2025), so they are about a year older than CBRE's. Whether power is included differs by market. AI-training facilities command about a 60% lease premium (JLL, Jan 2026). Live capacity and vacancy by city are on the operators and live capacity page.

Other cost and schedule factors

Grid connection, equipment lead times, labour, cooling and tax
FactorIndiaElsewhereSource
Grid connectionNo published India-wide lead time. National shortage was 0.03% in FY2025-26, but site substations and sanctioned load decide timing7 to 10 years in FLAP-D (Frankfurt, London, Amsterdam, Paris, Dublin; Cushman & Wakefield, Oct 2026); more than 4 years in primary markets (JLL)JLL; Cushman & Wakefield
Long-lead equipmentImported packages ran 2 to 4 weeks late in H1 2026Global average 33 weeks; generators 40-45 weeks; transformers 20-32 weeksTurner & Townsend; JLL
Construction labour and materialsTender prices forecast to rise 3 to 5%, driven mainly by labour and specialist MEP (mechanical, electrical, plumbing) demand; labour shortages of 30 to 35% across 71 projects in H1 2026; 10 to 15% cost escalation where imported raw materials are involvedn/aTurner & Townsend, 13 Aug 2026
Cooling and efficiencyHot, humid coastal hubs make cooling the biggest non-IT load; liquid cooling narrows the gapCool climates get more free-cooling hoursTurner & Townsend; Uptime Institute
TaxFinance Act 2026: tax exemption to tax year 2046-47 for a foreign company's income from using an Indian company's data centre services (conditions apply). Amendments became law on 17 Aug 2026 (Act No. 21 of 2026), but the prescribed conditions are not yet published (Nov 2026). General information, not tax advicen/aIncome-tax Act 2025, Schedule IV item 13C; Taxation and Other Laws (Amendment) Act 2026

Power companies are now building data centres

Energy companies are moving from selling power to data centres to building their own, usually next to their generation. Andhra Pradesh, the YEIDA belt in Uttar Pradesh and Gujarat are where land and firm green power come together. The government has also asked builders to site new campuses near power sources rather than only near the coast (MeitY, Sep 2026).

  • Round-the-clock green power needs storage or pumped hydro, so check which supplier can actually firm the supply, not only its solar and wind MW.
  • Nuclear is not an option for a 2026 to 2029 build: the SHANTI Act opened nuclear power to private companies in Dec 2025, but the small reactor rules and tender are unfinished and no data centre has a nuclear contract.
  • Gas captive plants are legal and idle gas capacity exists, but they bring LNG price risk, so treat gas as a bridge, not a plan.

Want this checked for your own site, power contract or launch plan? See DC advisory.

Sources for this section (36)
  1. MERC. Order in Case No. 75 of 2025 (MSEDCL tariff). 25 Mar 2026
  2. TNERC. Suo-motu Tariff Order No. 6 of 2025. 30 Jun 2025
  3. TGERC. Retail Supply Tariff Schedule FY2026-27. 2026
  4. UPPCL (UPERC-approved). Tariff and rate schedule approved for FY2026-27. 6 Jul 2026
  5. KERC. Tariff charges approved for the control period. 27 Mar 2025
  6. APERC. Tariff for retail sale of electricity, FY2026-27. 25 Mar 2026
  7. SP Group. Historical electricity tariff (Q4 2026). 1 Oct 2026
  8. Eurostat. Electricity prices for non-household consumers (nrg_pc_205). 9 Oct 2026
  9. US EIA. Electric Power Monthly, Table 5.6.A. 24 Sept 2026
  10. GlobalPetrolPrices. Electricity prices around the world. Mar 2026
  11. Turner & Townsend. Data centre construction cost index 2025-2026. 5 Nov 2025
  12. Turner & Townsend. India's construction shifts focus from cost to capacity. 13 Aug 2026
  13. CBRE. Global Data Center Trends 2026. 17 Jun 2026
  14. Cushman & Wakefield. India Data Centre H1 2025 Update (city rents). 2025
  15. Cushman & Wakefield and Invest India. Power Infrastructure for Data Centres in India and the Transition to Green Energy. 6 Oct 2026
  16. JLL. Global data center sector to nearly double to 200GW. 6 Jan 2026
  17. Gazette of India. Taxation and Other Laws (Amendment) Act 2026 (Act No. 21 of 2026). 17 Aug 2026
  18. ECB. Euro foreign exchange reference rates (USD, IDR, JPY, MYR, SGD). 13 Oct 2026
  19. RBI. FBIL reference rate, INR per US$ 95.2477. 13 Oct 2026
  20. pv magazine India. SECI's 1 GW FDRE-RTC power tender discovers ₹5.25/kWh tariff. 7 Aug 2026
  21. pv magazine. SECI discovers ₹5.99/kWh tariff for 4-hour peak renewable power. 24 Aug 2026
  22. Mercom India. Government extends ISTS charges waiver for renewable projects hit by grid delays. 22 Apr 2026
  23. LiveLaw. Karnataka High Court strikes down 2022 Green Energy Open Access Rules. Jan 2025
  24. pv magazine India. CleanMax and STT GDC India scale renewable energy partnership beyond 130 MW. 1 Apr 2026
  25. Renewable Watch. CleanMax to supply clean energy to Iron Mountain's data centers in India. 7 May 2026
  26. pv magazine India. Meta and CleanMax partner on 900 MW of solar and wind power capacity in India. 10 Jun 2026
  27. pv magazine. ReNew plans polysilicon manufacturing and 1 GW green hyperscale data centre in Andhra Pradesh. 13 Nov 2026
  28. Indian Infrastructure. ReNew signs ₹700 billion MoU with Maharashtra for a green integrated data centre park in MMR. 13 Oct 2026
  29. Tata Power. Tata Power advances 2.8 GW data centre opportunity pipeline across 18 data centre players. 14 Oct 2026
  30. SolarQuarter. NTPC Green Energy signs MoU with Nxtra to supply round-the-clock renewable power to data centers. 25 Mar 2026
  31. Bharti Airtel. Nxtra by Airtel signs partnership with AMPIN Energy Transition for ISTS solar-wind hybrid supply. Jul 2025
  32. DCD. Digital Edge signs 83 MW solar PPA with Hexa to power data center in Navi Mumbai. 26 Feb 2026
  33. NSE. Waaree Renewable Technologies: intimation of incorporation of step-down subsidiaries. 12 Sept 2026
  34. Indian Infrastructure. Waaree Green Data Centers incorporates two new subsidiaries for AI-ready data centre business. 17 Sept 2026
  35. Indian Infrastructure. Government urges Microsoft to locate future data centres near power sources. 22 Sept 2026
  36. World Nuclear News. Deadline extended to allow wider participation in Indian small reactor RFP. 2026

Power, build and rent costs

Frequently asked questions

  • On FY2026-27 industrial tariffs, indicative all-in prices run from about ₹6.2 per kWh (US$0.065) in Andhra Pradesh to ₹10.9 (US$0.114), Maharashtra's average billing rate for high-tension industry. Uttar Pradesh is about ₹6.6 to ₹7.7, Karnataka about ₹7.5 and Telangana about ₹7.8 to ₹8.8, while Tamil Nadu is about ₹9.0 on FY2025-26 rates. Our state estimates assume a flat 24x7 load at 85% load factor and exclude electricity duty, fuel adjustment and open access charges.

  • It is cheaper than Singapore and Europe, and in the same range as US states. Singapore's regulated rate is US$0.184 to US$0.192 per kWh (SP Group, Q4 2026), and users taking 70 to 150 GWh a year pay an average US$0.201 in Ireland, US$0.154 in Germany and US$0.140 in the Netherlands (Eurostat, H1 2026). US industry pays an average US$0.101 in Virginia and US$0.071 in Texas (US EIA, Jul 2026). Foreign figures use different bases, so treat them as a guide, not a like-for-like quote.

  • Each state distribution company (DISCOM) decides whether your connection is billed as industrial or commercial, and the gap can be large. In Maharashtra, high-tension (HT) commercial supply averages ₹16.74 per kWh against ₹10.88 for HT industry in FY2026-27, about 54% more (MERC). In Karnataka the current order makes HT commercial slightly cheaper than industry, and several state data centre policies, such as Tamil Nadu's 2021 policy, help secure industrial treatment. This is general information, not legal advice: get the category confirmed in writing for each connection.

  • About US$7.4m per MW (about ₹70 crore), within a range of US$5.9m to US$9.0m, excluding land and IT equipment (Cushman & Wakefield, 2026). On the same basis Malaysia costs US$9.6m, the USA US$15.2m and Japan US$16.0m, so a 100 MW build in India costs about US$220m less than in Malaysia. Turner & Townsend puts Mumbai at US$6.64m (cited Feb 2026) against US$14.5m in Singapore (Nov 2025); compare within one source, as specifications differ. Indian tender prices are forecast to rise 3 to 5%, driven mainly by labour and specialist mechanical, electrical and plumbing (MEP) work (Turner & Townsend, 13 Aug 2026).

  • Mumbai rents were ₹7,000 to ₹10,000 per kW a month (US$73 to US$105) for 250 kW to 1 MW and ₹6,000 to ₹7,500 (US$63 to US$79) for 5 MW or more, while Chennai, Hyderabad and Delhi NCR ranged from ₹6,000 to ₹8,500 (Cushman & Wakefield, H1 2025). CBRE's Q1 2026 asking rents were US$190 to US$235 in Northern Virginia, US$235 to US$265 in Frankfurt and US$330 to US$475 in Singapore. The Indian figures are about a year older, and whether power is included differs by market. Space for AI training commands about a 60% lease premium (JLL, Jan 2026).

  • Generally yes, and most do it through captive or group captive deals with independent power producers such as CleanMax, AMPIN, Hexa Climate or Tata Power, taking a 26% stake so the cross-subsidy and additional surcharges fall away (26%+ ownership and 51%+ consumption). Round-the-clock green power cleared at ₹5.25 to ₹5.26 per kWh in SECI's 1 GW tender (Aug 2026), up from about ₹4.5 to ₹4.7 in late 2024, before transmission, wheeling and surcharges. Third-party open access adds a cross-subsidy surcharge of ₹1.37 to ₹2.11 per kWh and wheeling of ₹0.81 to ₹1.04 in the states we checked, and each state regulator's own rules decide eligibility. This is general information, not legal advice, and we found no sourced all-in landed cost.

FlexiCloud DC advisory

Planning capacity in India?

FlexiCloud DC advisory can check the tariff category, green power options, power producer offers and power pass-through terms in your own colocation or power offer before you sign.

More from the India data centre guide

  • Operators and live capacity

    Live MW and vacancy for seven cities, led by Mumbai with 890 MW (H1 2026), plus live capacity, pipeline and owners for 14 major operators, each figure with its date and source.

  • Why India: outlook and risks

    India produces nearly 20% of the world's data but hosts about 3% of its data centres (Jun 2025). See the capacity forecasts to 2030, the demand behind them, and the risks: grid delays, water, unsettled rules, vacancy and unbuilt announcements.

  • Neocloud entry guide

    Entry models from colocation to build-to-suit, the Indian and US rules that apply (CERT-In, DPDP, export controls), IndiaAI reference GPU prices, verified state incentives and a 14-point checklist. Also why the 2047 tax exemption probably does not fit a neocloud that owns its GPUs.

Capacity is being built. Choosing where to run still matters.

More supply means more choice of site, region and provider, not less need for someone to help you pick. Whether you are planning your own capacity in India or need GPUs now, we deal with the operators and providers so you do not have to.