India Data Centre Market Guide 2026
India had about 1.6 to 1.8 GW of data centre capacity live in mid-2026, about half of it in Mumbai (JLL; Cushman & Wakefield). This guide tracks 75 projects from 31 developers that are building or planning more, and links to seven topic guides, from the main operators to power costs and how a GPU cloud can enter India. Every figure is sourced and dated.
We keep built capacity and announcements apart. Most of the money pledged for India is still a plan.
By Vinod Chacko, Founder and CEO · Last updated . Rupee to dollar conversions use ₹95.25 per US$ (FBIL reference rate, 13 Oct 2026).
Need GPUs before these projects come online? We source B300 nodes and B200 nodes in North America, the UK, Europe, India, Asia Pacific and the Gulf, and confirm availability and lead time for your region before you order.
Terms used in this guide (29)
- Neocloud
- A cloud company built mainly to rent out GPU compute for AI, as opposed to a general-purpose hyperscaler.
- Hyperscaler
- The largest cloud providers: AWS, Microsoft Azure, Google Cloud and similar.
- MW: IT load vs total power
- IT load is the power available to servers. Total power adds cooling and losses and is often 30 to 50% higher. Developers quote either.
- Colocation
- Renting space, power and cooling in someone else's data centre for your own servers.
- Powered shell, white space
- A powered shell is a building with grid power but no fit-out. White space is the finished hall floor where racks stand.
- Energisation, sanctioned load
- Energisation is when the utility actually switches power on. Sanctioned load is the maximum power it has approved for the connection.
- DISCOM
- A state electricity distribution company. It supplies and bills most large users.
- HT, EHV, HV-2
- High-tension (usually 11 to 33 kV) and extra-high-voltage supply; higher voltage usually means a lower tariff. HV-2 is Uttar Pradesh's category for large and heavy power users.
- Open access, wheeling, cross-subsidy surcharge
- Open access lets a large user buy power from a generator other than its DISCOM. Wheeling is the fee for using the DISCOM's wires; the cross-subsidy surcharge compensates the DISCOM for the customer it loses.
- Captive, group captive
- A power plant at least 26% owned by the users who consume at least 51% of its output. It is exempt from some surcharges.
- ASN (AS number)
- Autonomous System Number: the identifier a network needs to exchange traffic directly with other networks.
- IX (internet exchange)
- A place where networks connect to swap traffic directly instead of paying a carrier to carry it.
- Cross-connect, meet-me room
- A cross-connect is a cable from your rack to another network in the same building. The meet-me room is where those cables are joined.
- Cloud on-ramp
- A private link into a public cloud: AWS Direct Connect, Azure ExpressRoute, Google Cloud Interconnect, Oracle FastConnect.
- Cable landing station
- The building where a subsea cable comes ashore and joins land networks.
- Design vs lit capacity
- Design capacity is the most a cable could carry once every fibre pair is fully equipped. Lit capacity is what has been switched on with equipment; in TRAI's figures, activated capacity is the part of that in use.
- Gbps, Tbps
- Gigabits and terabits per second, the units for network capacity. 1 Tbps is 1,000 Gbps.
- CERT-In
- India's national cyber-security agency. Its 2022 directions set incident-reporting and log-keeping rules.
- DPDP, significant data fiduciary
- The Digital Personal Data Protection Act 2023 and its 2025 Rules, India's privacy law. A significant data fiduciary is a large or sensitive data handler the government designates for extra duties.
- MeitY, empanelment, STQC
- MeitY is the Ministry of Electronics and IT. Empanelment is its approved list of cloud providers for government work, after an audit by STQC, its testing body.
- IFSC, GIFT City
- The International Financial Services Centre at GIFT City, Gandhinagar, which has its own tax and regulatory regime.
- GO
- Government order: how a state allots land or notifies a policy.
- FY (Indian financial year)
- April to March. FY2026-27 runs from 1 Apr 2026 to 31 Mar 2027.
- H1, H2
- The first half (January to June) and second half (July to December) of a calendar year.
- Lakh, crore
- 1 lakh is 100,000 and 1 crore is 10 million. ₹1 lakh crore is ₹1 trillion, about US$10.5bn at ₹95.25 per US$.
- Capex
- Capital expenditure: money spent on buildings and equipment, as opposed to running costs.
- MEP
- Mechanical, electrical and plumbing: the building services trades on a data centre build.
- Country Group A:5, D:5
- Groups of countries in the US export rules. India is in Group A:5 and in no D group. A US licence for advanced AI chips is needed for customers headquartered in China, Macau or another D:5 country.
- Not announced, Not disclosed
- In the tracker: the developer has published no date (Not announced) or no MW figure (Not disclosed). We do not guess.
At a glance
India data centres at a glance
Eight numbers that frame the market. Each has a date and a source. H1 2026 means January to June 2026, and ₹1 lakh crore is ₹1 trillion.
- Data centre capacity live in India
- 1.6 to 1.8 GW
- Mid-2026. JLL 1.6 GW (Aug 2026); Cushman & Wakefield 1,789 MW (H1 2026)
- Operators and live capacity
- Under construction (509 MW) or planned (3,351 MW) to 2030
- 3.86 GW
- H1 2026. Cushman & Wakefield
- Operators and live capacity
- Most forecasts for 2029-2030
- 4 to 6 GW
- 2026 forecasts. CareEdge, Cushman & Wakefield, JLL, Economic Survey 2025-26
- Why India: outlook and risks
- Colocation vacancy in the top 7 cities (Mumbai 7.9%)
- 14.9%
- H1 2026. Cushman & Wakefield
- Operators and live capacity
- AI and cloud pledges from AWS, Microsoft and Google, mostly 2026 to 2030 (about ₹5.4 lakh crore, or ₹5.4 trillion). Pledges, not built capacity.
- US$56bn+
- Oct 2026. Amazon, Microsoft, Google releases
- Hyperscaler investment
- Grid power for large users in six data centre states (US$0.065 to 0.114)
- ₹6.2 to ₹10.9 per kWh
- FY2025-26 to FY2026-27 tariffs. State tariff orders; FlexiCloud estimate of all-in rate
- Power, build and rent costs
- International subsea cables live in India; 5 more planned
- About 15
- 14 Oct 2026. TeleGeography
- Subsea cables
Topic guides
Explore the guide by topic
Seven topic guides, each answering one question a buyer or seller asks about India. Each has dated key facts, tables, sources and its own FAQ.
Operators and live capacity
Live MW and vacancy for seven cities, led by Mumbai with 890 MW (H1 2026), plus live capacity, pipeline and owners for 14 major operators, each figure with its date and source.
Why India: outlook and risks
India produces nearly 20% of the world's data but hosts about 3% of its data centres (Jun 2025). See the capacity forecasts to 2030, the demand behind them, and the risks: grid delays, water, unsettled rules, vacancy and unbuilt announcements.
Hyperscaler investment
Amazon, Microsoft and Google have pledged more than US$56bn for AI and cloud in India, mostly for 2026 to 2030 (Oct 2026). See each pledge, what is already live, who else is investing and why.
Power, build and rent costs
Grid power in India is mid-priced, building is cheap and colocation rent is low by global standards. See FY2026-27 state power tariffs, build cost per MW and city colocation rents, set against Singapore, Europe, the US and other Asian markets.
Subsea cables
About 15 international cables are live in India, mainly landing in Mumbai and Chennai, and 5 more are planned (Oct 2026). See every live and upcoming cable, landing stations by city, repair times and what it means for choosing a data centre site.
Connectivity and latency
Where India's networks meet, what an internet exchange port costs, which buildings host AWS, Azure, Google Cloud and Oracle on-ramps, and typical latency between cities. Mumbai leads: DE-CIX had 451 networks there on 14 Oct 2026.
Neocloud entry guide
Entry models from colocation to build-to-suit, the Indian and US rules that apply (CERT-In, DPDP, export controls), IndiaAI reference GPU prices, verified state incentives and a 14-point checklist. Also why the 2047 tax exemption probably does not fit a neocloud that owns its GPUs.
Projects tracker
India data centre projects tracker
75 projects from 31 developers that are under construction, expanding or announced, each re-checked in October 2026. Live capacity is on the operators and live capacity page.
MW totals add the figure each developer gives for the project, often a whole campus, so they run well above market counts of halls actually being built. 9 projects do not disclose MW and are left out.
Scroll sideways to see all 8 columns.
| Anant Raj | Manesar, Panchkula & Rai campuses | Manesar (Gurugram), Panchkula and Rai (Sonipat), Haryana | Haryana / NCR | 279 MW | Anant Raj Ltd (listed); DC arm to be demerged into Ashok Cloud | Under construction or development: 63 MW targeted by end-FY27 and 117 MW by FY28Details28 MW IT live; sources conflict on the remainder (279 to 329 MW) | Commissioning: 2026 to 2032 |
| Sify Technologies | Rabale campus, Towers 6 to 12 | Rabale, Navi Mumbai | Navi Mumbai | 276 MW | Sify Infinit Spaces (Sify Technologies, Nasdaq: SIFY); IFC loan Jun 2026 | Under construction or development: T6/T7 and T11/T12 under construction or advanced developmentDetailsT1 to T5 built (101.26 MW IT); 377+ MW IT design | Commissioning: Not announced (phased) |
| Yotta Data Services | Greater Noida park: D2 + D4 | Greater Noida, Uttar Pradesh | NCR / Noida | 180 MW | Hiranandani Group | Under construction or development: D2 (60 MW) due 2026, not yet announced liveDetailschecked 14 Oct 2026; D4 (120 MW) under construction (reported) | Commissioning: 2026 to 2027 |
| Reliance Industries | Jamnagar AI data centre, first phase | Jamnagar, Gujarat | Gujarat | 120 MW | Reliance Industries / Reliance Intelligence | Under construction or development: Under constructionDetailsmore than 120 MW due H2 2026, not yet announced live; multi-GW planned (NVIDIA, 2023: eventually 2,000 MW); separate 168 MW built-to-suit DC for Meta, option to scale (RIL, Jun 2026) | Commissioning: H2 2026 (first phase) |
| Princeton Digital Group (PDG) | MU2 Navi Mumbai | Navi Mumbai, Maharashtra | Navi Mumbai | 120 MW | Warburg Pincus (largest), Stonepeak, OTPP, Mubadala | Under construction or development: Construction started Apr 2026 (single 5-storey building) | Commissioning: Not announced |
| Digital Edge | Navi Mumbai campus (BOM1 to BOM3) | Navi Mumbai, Maharashtra | Navi Mumbai | 120 MW | Stonepeak | Under construction or development: BOM2 topped out and BOM3 started (Aug 2026)Detailsclose to 120 MW across BOM1 to BOM3, including live BOM1 (not split out); 400 MW campus plan | Commissioning: 2026 to 2028 (estimate) |
| Sify Technologies | Noida 02 campus, remaining towers | B-11/12/13, Sector 132, Noida | NCR / Noida | 104 MW | Sify Infinit Spaces | Under construction or development: 2 more towers to come (130+ MW IT design)DetailsTower B live (25.92 MW IT built) | Commissioning: Not announced |
| Sify Technologies | Chennai 02 campus, remaining towers | SIPCOT IT Park, Siruseri, Chennai | Chennai | 104 MW | Sify Infinit Spaces; IFC loan Jun 2026 | Under construction or development: More towers to come (130+ MW IT design)DetailsTower B live (25.92 MW IT built) | Commissioning: Not announced |
| Princeton Digital Group (PDG) | MU1 Navi Mumbai expansion | Airoli, Navi Mumbai | Navi Mumbai | 100 MW | Warburg Pincus (largest), Stonepeak, OTPP, Mubadala | Under construction or development: First phase of a 100 MW expansion under constructionDetails50 MW live in 2 buildings | Commissioning: 2026 (first phase) |
| CtrlS Datacenters | Mumbai DC6 & DC7 (Mahape campus) | TTC MIDC Mahape, Navi Mumbai | Navi Mumbai | 95 MW | CtrlS (founder-led) + CPP Investments | Under construction or development: Under construction (DC6 & DC7)DetailsDC1 to DC5 live | Commissioning: 2026 to 2027 |
| STT GDC India | Navi Mumbai 2 & 3 | MIDC Mahape, Navi Mumbai | Navi Mumbai | 91 MW | STT GDC (KKR 75% + Singtel 25% since Sep 2026) | Under construction or development: Under development (ground broken Nov 2024)DetailsNavi Mumbai 1 (28 MW IT) appears live | Commissioning: 2026 to 2027 |
| Iron Mountain Data Centers (ex-Web Werks) | MUM-3 AI hyperscale campus | Mumbai area (2023 plan named Rabale, Navi Mumbai) | Navi Mumbai | 85 MW | Iron Mountain (100% owner) | Under construction or development: Ground broken Jan 2026 (reported)Details85 MW | Commissioning: 2027 to Q1 2028 |
| Yotta Data Services | NM2 (Panvel park) | Hiranandani Fortune City, Panvel, Navi Mumbai | Navi Mumbai | 80 MW | Hiranandani Group | Under construction or development: Fit-out under way (core and shell ready)Details75 to 80 MW reported; NM1 (52 MW IT) live | Commissioning: 2026 to 2027 |
| AirTrunk (Lumina CloudInfra) | BOM1 Navi Mumbai (ex-Lumina) | Navi Mumbai, Maharashtra | Navi Mumbai | 62 MW | Blackstone + CPP Investments (AirTrunk owners) | Under construction or development: About 60 MW reported ready (Jan 2026 press)Details62+ MW campus; AirTrunk lists the site but no launch announced by 14 Oct 2026 | Commissioning: 2026 |
| Navi Mumbai leased DC (EverYondr Mumbai 1) | MIDC, Navi Mumbai | Navi Mumbai | 60 MW | Google as tenant (Raiden Infotech, 28-year lease); built by EverYondr | Under construction or development: Under constructionDetails60 MW total and 30 MW Phase 1 reported, not confirmed; completion slipped from 2025 | Commissioning: 2026 to 2027 | |
| AdaniConneX | Noida campus | Sector 62, Noida | NCR / Noida | 50 MW | Adani Enterprises + EdgeConneX (JV) | Under construction or development: Partly operationalDetails50 MW is the whole campus, including live halls; live MW not disclosed | Commissioning: 2025 to 2027 |
| STT GDC India | Palava campus, Phase 1 | Palava, Thane district (MMR), Maharashtra | Mumbai | 50 MW | STT GDC (KKR 75% + Singtel 25% since Sep 2026) | Under construction or development: Ground broken Mar 2026 (50 MW IT)DetailsSTT lists 171 MW under development; campus designed for about 400 MW | Commissioning: Not announced |
| STT GDC India | Noida 2 & 3 | Sector 143A, Noida | NCR / Noida | 50 MW | STT GDC (KKR 75% + Singtel 25% since Sep 2026) | Under construction or development: Under developmentDetailsNoida 1 (17 MW IT) live | Commissioning: Not announced |
| Sify Technologies | Vizag AI edge DC + open cable landing station | Rushikonda-Madhurawada IT Park, Visakhapatnam | Andhra Pradesh | 50 MW | Sify Infinit Spaces | Under construction or development: Foundation stone laid Oct 2025 (₹1,500 crore, two phases) | Commissioning: Not announced |
| Nxtra by Airtel | Mahape hyperscale park (MUM 4) | TTC Industrial Area, Mahape, Navi Mumbai | Navi Mumbai | 42 MW | Bharti Airtel (control); Alpha Wave, Carlyle, Anchorage (US$1bn round agreed Mar 2026) | Under construction or development: PhasedDetailsfirst tower built 2025 (Baxtel); Nxtra lists MUM 3 at 18 MW IT and MUM 4 at 42 MW IT without saying which is live | Commissioning: 2026 to 2027 |
| Iron Mountain Data Centers (ex-Web Werks) | CHN-1 & CHN-2 (Ambattur campus) | Ambattur, Chennai | Chennai | 42 MW | Iron Mountain (100% owner) | Under construction or development: CHN-1 (23.2 MW) topped out Apr 2026Detailsgo-live expected 2026, not announced by 14 Oct 2026; CHN-2 (19 MW) from 2028; 42 MW power | Commissioning: 2026 to 2028 |
| Sify Technologies | Bengaluru 02 campus | KIADB Aerospace Park, Bengaluru | Bengaluru | 40 MW | Sify Infinit Spaces | Under construction or development: Under development per Sify (FY26 integrated report)Detailsno date disclosed | Commissioning: Not announced |
| L&T-Vyoma (ex-Cloudfiniti) | Mahape campus, Phase 1 | Mahape, Navi Mumbai | Navi Mumbai | 40 MW | Larsen & Toubro (DC business moving to Vyoma.AI) | Under construction or development: Ground broken 21 Jan 2026Detailsfirst step to a 100 MW campus | Commissioning: Not disclosed |
| CapitaLand (CLINT) | CapitaLand DC Mumbai, Tower 2 | Airoli, Navi Mumbai | Navi Mumbai | 37 MW | CapitaLand India Trust (79.8%) + CapitaLand India Data Centre Fund (20.2%) | Under construction or development: Completion 4Q 2026, handover 1H 2027Detailspre-leased to a hyperscaler; Tower 1 (34 MW IT) live | Commissioning: 2026 to 2027 |
| STT GDC India | Navi Mumbai 4 | MIDC Mahape, Navi Mumbai (per STT) | Navi Mumbai | 36 MW | STT GDC (KKR 75% + Singtel 25% since Sep 2026) | Under construction or development: Under development per STT websiteDetailsno dated announcement | Commissioning: Not announced |
| CapitaLand (CLINT) | CapitaLand DC Chennai (Ambattur) | Ambattur, Chennai | Chennai | 34 MW | CapitaLand India Trust (79.8%) + CapitaLand India Data Centre Fund (20.2%) | Under construction or development: Core and shell works in progressDetails34 MW IT (53 MW power); no tenant signed (Jul 2026) | Commissioning: 4Q 2026 (target) |
| NTT Data GDC | Noida 2, Building B | Plot 18, Noida data centre corridor | NCR / Noida | 30.4 MW | NTT DATA (Japan) | Under construction or development: May already be live (Baxtel)DetailsNTT has not announced it; Building A (22.4 MW IT) live since Jan 2024 | Commissioning: 2025 to 2026 |
| Techno Electric | Noida data centre | Noida, Uttar Pradesh | NCR / Noida | 30 MW | Techno Electric (listed) | Under construction or development: Full 30 MW launching 2026 per companyDetailsPhase 1 (0.8 MW) live | Commissioning: 2026 to 2027 |
| CapitaLand (CLINT) | CapitaLand DC ITPH | International Tech Park Hyderabad, Madhapur | Hyderabad | 27 MW | CapitaLand India Trust (79.8%) + CapitaLand India Data Centre Fund (20.2%) | Under construction or development: Phase 1 nearing completion (Jul 2026)Detailscore and shell plus Phase 1 M&E; completion not announced by 14 Oct 2026; 27 MW IT (42 MW power) | Commissioning: 2026 (3Q target passed) |
| Nxtra by Airtel | Kolkata hyperscale DC | Action Area IIE, New Town (Bengal Silicon Valley), Kolkata | Kolkata | 25 MW | Bharti Airtel (control); Alpha Wave, Carlyle, Anchorage (US$1bn round agreed Mar 2026) | Under construction or development: Under construction since Nov 2022Detailsoperations expected about Sep 2026; no launch announced by 14 Oct 2026 | Commissioning: 2026 |
| STT GDC India | Chennai 4 (Ambattur campus) | Ambattur, Chennai | Chennai | 18 MW | STT GDC (KKR 75% + Singtel 25% since Sep 2026) | Under construction or development: Ground broken Feb 2026Details40 MW already live on this campus; campus potential about 130 MW | Commissioning: Not announced |
| NTT Data GDC | Chennai 2, Building B | Ambattur, Chennai | Chennai | 17.4 MW | NTT DATA (Japan) | Under construction or development: Under constructionDetailsBuilding A (17.4 MW IT) live since 2023 | Commissioning: 2027 (estimate) |
| CtrlS Datacenters | Bhopal edge data centre | Badwai IT Park, Bhopal | Bhopal | 12 MW | CtrlS | Under construction or development: Ground broken Apr 2025 (phased) | Commissioning: 2026 to 2027 (estimate) |
| Pi Data Centers | Mumbai data centre | Mumbai (site not disclosed) | Mumbai | 3 MW | Pi Data Centers | Under construction or development: Launched Apr 2026Detailsgo-live scheduled Aug 2026, not announced by 14 Oct 2026 | Commissioning: 2026 |
| Visakhapatnam AI hub (gigawatt-scale campus) | Tarluvada, Adavivaram and Rambilli, Visakhapatnam / Anakapalli districts, Andhra Pradesh | Andhra Pradesh | Not disclosed | Google (via Raiden Infotech); AdaniConneX and Nxtra by Airtel as partners | Under construction or development: Under construction (ground broken 28 Apr 2026)Detailsno phase MW published; about 1 GW reported for the full campus, Google says gigawatt-scale | Commissioning: 2026 to 2030 | |
| AdaniConneX | Hyderabad campus (Elkatta) | Elkatta, near Shadnagar, Rangareddy district, Telangana | Hyderabad | Not disclosed | Adani Enterprises + EdgeConneX | Under construction or development: Partly operational (2025)Detailsfurther phases planned; MW not disclosed | Commissioning: 2025 to 2028 |
| NTT Data GDC | NAV2 Navi Mumbai campus (remaining buildings) | MIDC Road, Navi Mumbai | Navi Mumbai | Not disclosed | NTT DATA (Japan); Tokyo Century co-investor | Under construction or development: Partly liveDetailscampus designed for 336 MW IT (500 MW power); unbuilt MW not disclosed | Commissioning: 2025 to 2027 |
| Amazon Web Services (AWS) | Hyderabad region expansion (Bharat Future City) | Bharat Future City, Ranga Reddy district, Telangana | Hyderabad | Not disclosed | Amazon | Under construction or development: Ground broken 15 Jul 2026DetailsMW not disclosed | Commissioning: 2026 to 2030 (investment period) |
| AirTrunk (Lumina CloudInfra) | Raigad AI campus (Pen Growth Centre) | Pen, Raigad district (MMR), Maharashtra | Mumbai | 3 GW | Blackstone + CPP Investments (AirTrunk owners) | Announced: Letter of intent for land (Maharashtra, 1 Jun 2026)Detailsabout ₹2 lakh crore reported | Commissioning: Not announced (AirTrunk has a 5 GW India plan) |
| TeraNova DC (Hillhouse) | India platform, sites not yet disclosed | Maharashtra, Telangana, Andhra Pradesh, Delhi NCR and Gujarat | Multiple states | 2 GW | Hillhouse Investment (Singapore); CEO Sanjay Bhutani | Announced: Platform launched 15 Oct 2026: over 2 GW and about US$12 to 15bn by 2032Detailsno sites, MW per site or first go-live disclosed yet | Commissioning: By 2032 |
| Cortex DC (The Chatterjee Group) | India AI-ready platform, sites not yet disclosed | Not disclosed (the company says its capacity is anchored on the Golden Quadrilateral corridor) | Sites not disclosed | 2 GW | The Chatterjee Group (TCG, New York); CEO Rahul Sharma | Announced: Platform launched 22 Oct 2026: 2 GW (IT or total power not stated)Detailsfirst facility targeted within 18 months of first shovel, no start date yet; 51% of energy from green sources; no sites, investment or MW per site disclosed | Commissioning: About 7 years (per PTI) |
| DigitalConnexion | Vizag AI-native campus | Visakhapatnam, Andhra Pradesh | Andhra Pradesh | 1 GW | Brookfield + Reliance Industries + Digital Realty (JV) | Announced: MoU with AP Govt (Nov 2025)Detailsabout US$11bn by 2030; 400 acres | Commissioning: 2030 (target) |
| TCS HyperVault | Hyderabad AI campus (Bharat Future City) | Bharat Future City, Hyderabad, Telangana | Hyderabad | 1 GW | TCS + TPG (up to ₹18,000 crore platform, Nov 2025); OpenAI first customer (100 MW, Feb 2026) | Announced: Land acquired (264 acres, Sep 2026)Detailsup to 1 GW, phased by demand | Commissioning: Not announced (phased) |
| AM Group (AM Intelligence Labs) | Jewar AI compute hub (YEIDA) | Sector 28, YEIDA, Jewar, Uttar Pradesh | NCR / Noida | 1 GW | AM Group (Greenko founders) | Announced: Letter of intent for land (YEIDA, Feb 2026)DetailsPhase I 384 MW (₹26,910 crore) targeted 2028 | Commissioning: 2028 to 2030 (target) |
| CtrlS Datacenters | Chandan Valley campus | Chandanvelly, near Hyderabad, Telangana | Hyderabad | 612 MW | CtrlS (founder-led) + CPP Investments | Announced: Announced Jan 2025DetailsPhase 1 power (250 MW) sanctioned; ICRA (Oct 2026) lists 2 CtrlS DCs under construction in Hyderabad without naming the sites | Commissioning: Not announced |
| Sify Technologies | Vizag hyperscale campus (Paradesipalem) | Paradesipalem, Visakhapatnam | Andhra Pradesh | 500 MW | Sify Infinit Spaces | Announced: State-approved (SIPB Jul 2025; about ₹15,266 crore)Details12.4 of 25 extra acres allotted conditionally (Jun 2026) | Commissioning: Not announced |
| Trentar (Dorf Ketal Group) | Green hyperscale DC park | Maharashtra (site not disclosed) | Maharashtra (site not disclosed) | 500 MW | Dorf Ketal Group | Announced: MoU with Maharashtra Govt (Oct 2026; ₹30,000 crore)Detailsfeasibility studies pending | Commissioning: Not announced |
| Amazon Web Services (AWS) | Taloja campus (Asode and Burdul) | Taloja, Navi Mumbai, Maharashtra | Navi Mumbai | 473 MW | Amazon | Announced: Environmental clearance applied Apr 2026Details473 MW is a power requirement, not IT load | Commissioning: 2027 to 2030 (estimate) |
| Indian GPU cloud (Blackstone-backed) | Hyderabad AI cluster (with NTT DATA) | Hyderabad, Telangana | Hyderabad | 400 MW | Blackstone (majority, Feb 2026); NTT DATA + Telangana Govt MoU | Announced: Announced (MoU, Apr 2025, ₹10,500 crore)Detailsno construction reported | Commissioning: Not announced |
| Digital Edge | Palava campus | Palava, Thane district (MMR), Maharashtra | Mumbai | 270 MW | Stonepeak | Announced: Land bought (about 30 acres, Jul 2026, about ₹1,000 crore)Detailsno timeline | Commissioning: Not announced |
| Sify Technologies | Hyderabad 02 campus | Fab City, Hyderabad | Hyderabad | 250 MW | Sify Infinit Spaces | Announced: Planned (250+ MW IT design)Detailsnot in Sify list of DCs under development (Jul 2026) | Commissioning: Not announced |
| AirTrunk (Lumina CloudInfra) | HYD1 Hyderabad | Hyderabad, Telangana | Hyderabad | 250 MW | Blackstone + CPP Investments (AirTrunk owners) | Announced: Under development (Jan 2026 press: two sites, about 250 MW)DetailsAirTrunk gives no MW | Commissioning: Not announced |
| AdaniConneX | Taloja AI campus | Taloja, Navi Mumbai, Maharashtra | Navi Mumbai | 240 MW | Adani Enterprises + EdgeConneX; a US AI cloud company is sole tenant | Announced: Announced Oct 2026: 3 x 80 MW buildings in designDetailsoption for 240 MW more | Commissioning: 2028+ (first phase mid-2028) |
| L&T-Vyoma (ex-Cloudfiniti) | Chennai AI campus expansion | Chennai (Kanchipuram district) | Chennai | 220 MW | Larsen & Toubro (DC business moving to Vyoma.AI) | Announced: Design and feasibility only (L&T filing, Aug 2026)DetailsPhase 1 designed for 250 MW with 150 MVA ready; 30 MW already live | Commissioning: Not announced |
| AirTrunk (Lumina CloudInfra) | MAA1 Chennai (Ambattur) | Ambattur, Chennai | Chennai | 216 MW | Blackstone + CPP Investments (AirTrunk owners) | Announced: Land bought (16 acres, Jan 2026)Details216 MW initial IT load; no construction start reported | Commissioning: Not announced |
| AirTrunk (Lumina CloudInfra) | Second Navi Mumbai site (Mahape) | Mahape, Navi Mumbai | Navi Mumbai | 120 MW | Blackstone + CPP Investments (AirTrunk owners) | Announced: Under development (Jan 2026 press)Detailspress puts the two Navi Mumbai sites at 180 MW in total | Commissioning: Not announced |
| Colt DCS | Navi Mumbai campus, later phases | Airoli, Navi Mumbai | Navi Mumbai | 112 MW | Colt DCS (Fidelity) + RMZ, 50:50 JV | Announced: Later phases planned, no construction date disclosedDetailsPhase 1 (22 MW IT) live since Sep 2023 | Commissioning: Not announced |
| STT GDC India | Devanahalli campus (KIADB land) | Devanahalli, Bengaluru | Bengaluru | 100 MW | STT GDC (KKR 75% + Singtel 25% since Sep 2026) | Announced: Announced by Karnataka Govt, 25 Sep 2026 (about ₹5,000 crore)Detailsno MoU or timeline reported | Commissioning: Not announced |
| STT GDC India | Hyderabad AI-ready campus | Meerkhanpet, Mucherla, Ranga Reddy district, Telangana | Hyderabad | 100 MW | STT GDC (KKR 75% + Singtel 25% since Sep 2026) | Announced: MoU with Telangana Govt (Jan 2025)Detailsup to ₹3,500 crore | Commissioning: Not announced |
| UPC Volt | Bharat Future City AI-ready DC | Bharat Future City, Hyderabad, Telangana | Hyderabad | 100 MW | UPC Renewables + VOLT Data Centers (JV) | Announced: MoU with Telangana Govt (Davos, Jan 2026; ₹5,000 crore) | Commissioning: Not announced |
| Colt DCS | Chennai campus | Ambattur, Chennai | Chennai | 96 MW | Colt DCS (Fidelity) + RMZ, 50:50 JV | Announced: Planned (10-acre site bought Mar 2024) | Commissioning: 2027 (target) |
| Princeton Digital Group (PDG) | HY1 Hyderabad | Hyderabad, Telangana | Hyderabad | 90 MW | Warburg Pincus (largest), Stonepeak, OTPP, Mubadala | Announced: Site acquisition announced Mar 2026Detailspower and key land approvals in place | Commissioning: Not announced |
| DigitalConnexion | Chennai campus, later buildings | Ambattur Industrial Estate, Chennai | Chennai | 80 MW | Brookfield + Reliance Industries + Digital Realty (JV) | Announced: Later buildings planned, no dates disclosedDetailsMAA10 phase 1 (20 MW) live since Jan 2024; 100 MW, 4-building campus | Commissioning: Not announced |
| Princeton Digital Group (PDG) | CH1 Chennai | North Chennai Metropolitan Area, Tamil Nadu | Chennai | 72 MW | Warburg Pincus (largest), Stonepeak, OTPP, Mubadala | Announced: Announced Sep 2024 (9.3 acres)Detailsno construction start confirmed | Commissioning: Not announced |
| AirTrunk (Lumina CloudInfra) | Chandivali data centres (2 buildings) | Chandivali, Mumbai | Mumbai | 60 MW | Blackstone + CPP Investments (AirTrunk owners) | Announced: Land acquiredDetailstwo 30 MW DCs planned (60 to 90 MW reported) | Commissioning: Not announced |
| CtrlS Datacenters | Kolkata campus, Phases 2 to 4 | Bengal Silicon Valley, New Town, Kolkata | Kolkata | 44 MW | CtrlS | Announced: PlannedDetailsPhase 1 (16 MW IT) live since Aug 2025; campus 60+ MW IT | Commissioning: Not announced |
| STT GDC India | Siruseri campus build-out (beyond Chennai 7) | SIPCOT IT Park, Siruseri, Chennai | Chennai | 37.8 MW | STT GDC (KKR 75% + Singtel 25% since Sep 2026) | Announced: PlannedDetailsChennai 7 Phase 1 (7.2 MW) live Feb 2026; campus designed for 45 MW | Commissioning: Not announced |
| DigitalConnexion | BOM10 Mumbai | Chandivali, Mumbai | Mumbai | 35 MW | Brookfield + Reliance Industries + Digital Realty (JV) | Announced: Operator lists Planned - 2026Details35 MW IT (40 MW power); no construction milestone found | Commissioning: 2026 to 2027 |
| AdaniConneX | Chennai 1, Building 2 | SIPCOT IT Park, Siruseri, Chennai | Chennai | 16 MW | Adani Enterprises + EdgeConneX | Announced: PlannedDetailsBuilding 1 (17 MW IT) already live; campus 33 MW IT | Commissioning: 2027 (target) |
| Techno Electric | Kolkata data centre | Kolkata, West Bengal | Kolkata | 13 MW | Techno Electric (listed) | Announced: PlannedDetailslaunching 2027 per company | Commissioning: 2027 |
| Reliance Industries | Vizianagaram AI data centre + cable landing station | Polipalli and Bhogapuram, Vizianagaram district, Andhra Pradesh | Andhra Pradesh | Not disclosed | Reliance Industries | Announced: Land allotted by state order, 20 May 2026Details854.97 acres; ₹1.08 lakh crore; MW not disclosed (press: about 1.5 GW) | Commissioning: Not announced |
| Nxtra by Airtel | New AI-ready Chennai campus | Chennai (site not disclosed) | Chennai | Not disclosed | Bharti Airtel (control); Alpha Wave, Carlyle, Anchorage (US$1bn round agreed Mar 2026) | Announced: In development per Airtel (Mar 2026)Detailssite and MW not disclosed | Commissioning: Not announced |
| Microsoft | Pune region expansion | Pune (Central India region) | Pune | Not disclosed | Microsoft | Announced: Expansion announced Dec 2025Detailscapacity and sites not disclosed | Commissioning: 2026 to 2029 |
| HCLTech + Sarvam AI | Odisha sovereign AI park data centre | Khurda district (near Bhubaneswar), Odisha | Odisha | Not disclosed | HCLTech + Sarvam AI; Govt of Odisha support | Announced: MoU Jul 2026 (₹14,257 crore incl. state assistance)DetailsMW not disclosed | Commissioning: Not announced |
| Sarvam AI | Tamil Nadu sovereign AI park | Chennai, Tamil Nadu | Chennai | Not disclosed | Sarvam AI + Govt of Tamil Nadu | Announced: MoU Jan 2026 (about ₹10,000 crore)DetailsMW not disclosed | Commissioning: Not announced |
Compiled by FlexiCloud from company announcements, regulatory filings, state government statements and, where nothing primary exists, trade press. MW is the figure the developer gives: IT load where stated, otherwise total power; the status says which where known. Announced includes MoUs, land deals and letters of intent that may change or not be built. Live capacity is left out where the operator splits it out; for AdaniConneX Noida and Hyderabad, Digital Edge BOM1 to BOM3 and NTT Noida 2 Building B the figure may include live halls.
Something missing, out of date, or wrong? Get in touch and we will add, correct or remove it. Last updated October 2026.
Totals as of 24 October 2026
| Status | Projects | MW given by developers |
|---|---|---|
| Under construction or development | 38 | About 2.5 GW |
| Announced (MoU, land, plan) | 37 | About 15.0 GW |
| Of these, MW not disclosed | 9 | Left out of the MW totals |
10.0 GW of the announced MW is 6 gigawatt-scale plans, led by AirTrunk at Raigad (3 GW, a letter of intent for land). Not comparable with market counts of halls being built; see How to read the tracker, below.
How to read the tracker
What the statuses and MW figures mean, and why the totals run above market counts
- Under construction or development: building work has started, or the operator lists the site as under development. The MW is usually the whole project or campus, not just the halls being built now.
- Announced: an MoU, land deal, letter of intent or plan, with no construction start found.
- MW is the figure the developer gives. Some quote IT load and some quote total power, which can be 30 to 50% higher. The status says which where it matters.
- The table opens with work under way, largest first. Use Show all, the filters or search to reach every row; Details under a status gives the full note.
- Not disclosed means we found no reliable MW figure. We do not guess.
- Gigawatt-scale announcements are plans. Treat them as intent, not supply.
- We re-checked every row in October 2026 against company releases, filings, regulator and state government documents and, where nothing primary exists, trade press. Live capacity is left out of the table where operators split it out.
- The 6 gigawatt-scale plans are AirTrunk at Raigad (3 GW, a letter of intent for land), TeraNova DC (Hillhouse's new multi-state platform, over 2 GW by 2032, no sites disclosed yet), Cortex DC (The Chatterjee Group's new platform, 2 GW over about seven years per PTI, no sites disclosed yet), AM Group at Jewar, DigitalConnexion at Visakhapatnam and TCS HyperVault at Hyderabad. Google's gigawatt-scale Visakhapatnam campus publishes no phase MW, so it is one of the projects left out of the MW totals.
- Why the totals are higher than the 509 MW market count: they add the MW each developer gives for the project, IT or power basis as stated, often several buildings or a whole campus, and include sites the operator lists as under development. For Reliance Jamnagar we count only the first phase (120 MW).
- Cushman & Wakefield counts only IT load physically being built in the top 7 cities: 509 MW under construction and 3,351 MW planned (H1 2026). The two measure different things.
What changed in the October 2026 update
| Change | Rows | Examples |
|---|---|---|
| Moved out: now live | 10 | CtrlS Chennai park (72 MW IT), Equinix MB3 Mumbai, Microsoft Hyderabad region, L&T-Vyoma Chennai (30 MW IT), Yotta GIFT City (2 MW) |
| Moved out: on hold or not verifiable | 4 | CapitaLand Bengaluru (on hold, Jul 2026), Nxtra Greater Noida, Bridge Data Centres Chennai, NxtGen Bengaluru/Hyderabad |
| Corrected | 48 | Sify Rabale now shows only unbuilt towers (276 MW); Nxtra Mahape uses Nxtra's own 42 MW; Microsoft Pune shows MW not disclosed |
| Added | 27 | PDG MU2, Digital Edge Navi Mumbai, AirTrunk Raigad (letter of intent), Reliance Vizianagaram, TCS HyperVault Hyderabad, Sify Vizag, and two new 2 GW platforms: TeraNova DC and Cortex DC |
The former OpenAI Stargate India row is now TCS HyperVault Hyderabad, where OpenAI is the first customer, so the same capacity is not counted twice.
Sources for this section (5)
- Company releases, filings and state government statements. With trade press where nothing primary exists. Developer names in the table link to their sites. 2023 to Oct 2026
- Inc42. US AI cloud company takes 240 MW at AdaniConneX Taloja. 6 Oct 2026
- Sify Infinit Spaces. Integrated Report 2025-26. Jul 2026
- CapitaLand India Trust. 1H 2026 results press release. 29 Jul 2026
- STT GDC India. Data centre locations: Mumbai, Noida, Chennai. Oct 2026
FlexiCloud DC advisory
Entering India? We help GPU clouds go from first question to racked GPUs
FlexiCloud sources dedicated NVIDIA GPU nodes across more than 10 partner providers in North America, the UK, Europe, India, Asia Pacific and the Gulf. That puts us in regular contact with Indian data centre operators, carriers and GPU buyers.
We use that network to help neoclouds, AI labs and cloud providers enter India with fewer surprises: the right site, power you can count on, a clear compliance path and customers to talk to.
Who this is for
GPU cloud companies, AI labs and cloud providers planning anything from a few racks to tens of MW in India.
What we help with
Site and DC partner selection
Shortlist campuses by city, rack density, liquid cooling, energisation date and carrier neutrality; arrange site visits; run the RFP
You getA comparison of offers on the terms that matter for GPUs, not just price per kW
Power and connectivity
Check sanctioned load and energisation evidence, tariff category and green power options; map carriers, exchanges, cloud on-ramps and subsea path diversity; collect cross-connect quotes
You getA power and network plan you can put into the contract
Regulatory and compliance path
Map entity structure, foreign investment, CERT-In, DPDP, MeitY empanelment, telecom and US export-control screening, and the 2047 data centre tax route, working with your Indian legal and tax advisers
You getA compliance checklist with owners and dates, for your Indian counsel to confirm
GPU supply
Source B200, B300 and other NVIDIA nodes through our provider network, including interim capacity while your own build comes online
You getCapacity on a timeline that matches your launch
Introductions to Indian customers
Introduce you to AI startups, enterprises and labs in our network that are looking for GPU capacity
You getWarm conversations with buyers. Introductions, not guaranteed demand
Commercial terms review
Review colocation, power and carrier offers for the terms that bite later: ramp schedule, power pass-through, energisation penalties, SLA credits, expansion rights and exit
You getA list of terms to fix before you sign, for your counsel to finalise
How it works
- 01
Call
A short call to understand your workload, MW or GPU count, timeline and target customers
- 02
Brief
We agree scope and terms in writing before any work starts
- 03
Shortlist
Sites, power and network options, with site visits
- 04
Negotiate
Support on commercial and technical terms with operators and carriers
- 05
Launch
Help with GPU supply, compliance set-up and first customer introductions
What to expect from us
- We do not own data centres, so we have no site of our own to sell you.
- How we are paid: GPU providers in our network pay us a commission when we place capacity with them, and a data centre operator or carrier may pay us a referral fee. If any party we recommend will pay us, we tell you in writing before you sign.
- We are not a law firm or tax adviser; we work alongside yours.
- We will tell you when a site, a timeline or a price does not hold up.
Planning capacity in India?
Tell us your GPU count or MW, preferred cities and timeline. We will come back with a first view of options.
FAQ
Frequently asked questions
About 1.6 to 1.8 GW of data centre capacity was live in mid-2026. JLL puts it at 1.6 GW (Aug 2026) and Cushman & Wakefield at 1,789 MW (H1 2026), with Mumbai holding about half. Cushman & Wakefield also counts 509 MW under construction and 3,351 MW planned to 2030 (H1 2026). AWS, Microsoft and Google have pledged more than US$56bn for AI and cloud in India, mostly for 2026 to 2030 (Oct 2026), but pledges are not built capacity.
The largest plans are six gigawatt-scale announcements: AirTrunk at Raigad near Mumbai (3 GW, a letter of intent for land), two new 2 GW platforms with no sites disclosed yet, TeraNova DC (Hillhouse, over 2 GW across five states by 2032) and Cortex DC (The Chatterjee Group, 2 GW over about seven years, per PTI), and about 1 GW each from AM Group at Jewar, DigitalConnexion at Visakhapatnam and TCS HyperVault at Hyderabad (tracker, 24 October 2026). Google is building a gigawatt-scale campus at Visakhapatnam (ground broken 28 Apr 2026) but publishes no phase MW. For live capacity, Mumbai, including Navi Mumbai, leads with 890 MW, and Hyderabad has the second-largest pipeline at 710 MW (Cushman & Wakefield, H1 2026).
MeitY says capacity rose from about 375 MW in 2020 to about 1,500 MW by 2025 (PIB, Mar 2026). Cushman & Wakefield counted 1,280 MW live in H1 2025 and 1,789 MW in H1 2026, though part of that rise is a change in what it counts in Bengaluru. CBRE expects about 2 GW by end-2026 (Oct 2026). Most forecasts for 2029 to 2030 fall between 4 and 6 GW; the Why India page of this guide compares them.
The tracker lists 75 projects from 31 developers that are under construction, expanding or announced, each re-checked in October 2026. It keeps two totals apart: about 2.5 GW under construction or development in 38 projects, and about 15.0 GW announced in 37 projects, 10.0 GW of which is 6 gigawatt-scale plans (24 October 2026). MW is the figure each developer gives, IT load or total power, and Not disclosed means we found no reliable figure. Use the filters or search to find a city, developer or status. These totals are not comparable with Cushman & Wakefield's 509 MW, which counts only IT load being built in the top 7 cities.
In two ways. If you need GPUs now, we source dedicated NVIDIA nodes, such as B200 and B300, through more than 10 partner providers in North America, the UK, Europe, India, Asia Pacific and the Gulf. If you are planning your own capacity, our DC advisory helps with site and partner selection, power and connectivity, the compliance path, commercial terms and introductions to Indian customers. We do not own data centres, and if any party we recommend will pay us, we tell you in writing before you sign. Start by booking a call.
Planning capacity in India?
Book an advisory callSources
Sources and method
Every figure on this page comes from a named source with a date. Each section lists its sources; in the tracker, developer names link to their sites. We prefer company releases, filings, regulators and government documents, then established research firms, then trade press.
Where sources disagree we show the range. Where a figure could not be verified we leave it out or say so. Money is shown in rupees and US dollars at ₹95.25 per US$ (FBIL reference rate, 13 Oct 2026) unless the source gave its own US$ figure.
Corrections are welcome. If you spot something out of date, tell us and we will check and update it.
Government and regulators
- Economic Survey 2025-26 (Ministry of Finance)
- Budget 2026-27 speech, Finance Bill 2026 and the Taxation and Other Laws (Amendment) Bill 2026 (via PRS)
- TRAI performance indicators and subsea cable recommendations
- PIB releases (MeitY, IndiaAI, DPDP, Pax Silica)
- CERT-In directions (2022)
- RBI payment data circular (2018) and FBIL reference rate
- SEBI cloud framework (2023)
- State electricity regulators: MERC, TNERC, TGERC, UPERC, KERC, APERC
- Tamil Nadu DC Policy 2021; Uttar Pradesh DC Policy 2026
- US BIS guidance and Federal Register rules
- ECB euro reference rates
- IndiaAI compute portal
Research firms
- Cushman & Wakefield (H1 2025 and H1 2026 updates; reports with Invest India, Oct 2026)
- JLL (India mid-year 2026; global outlook)
- CBRE (Global Data Center Trends 2026)
- Turner & Townsend (cost index and India insights)
- ICRA, CareEdge Ratings
- Uptime Institute
- TeleGeography
- PeeringDB
Company sources
- Releases and filings from Adani, Airtel, Amazon, CapitaLand India Trust, CtrlS, DigitalConnexion, Digital Edge, Equinix, Google, Iron Mountain, L&T, Meta, Microsoft, NTT DATA, Princeton Digital Group, Reliance Industries, Sify, STT GDC, Tata Group, Yotta and others
Trade press used where no primary source exists
- W.Media, DCD, Inc42, TechCrunch, Business Today, The News Minute, Baxtel, SubmarineNetworks
The tracker above and each topic page list the documents they rely on, with dates and links.
Capacity is being built. Choosing where to run still matters.
More supply means more choice of site, region and provider, not less need for someone to help you pick. Whether you are planning your own capacity in India or need GPUs now, we deal with the operators and providers so you do not have to.
DC advisory
Entering India with a GPU cloud?
We help you pick the site, check the power and connectivity, map the compliance path with your counsel and meet Indian buyers, from a few racks to tens of MW.